The developers of the Dunkin Donuts Park said the Hartford Stadium Authority (HSA) is the reason for mismangement of the project's $56 million budget and $10 million in cost overruns.
DoNo Hartford LLC and Centerplan, the developer of Dunkin' Donuts Park, responded to a letter critical of the company that was sent earlier this week by the Chairperson of the Hartford Stadium Authority (HSA).
Centerplan's CEO told NBC Connecticut exclusively the city hasn't lived up to its end of the deal that was signed back in February.
Charles Mathews with the HSA sent a letter this week accusing the company of mismanaging the $56 million budget, arguing there are now $10 million in cost overruns.
Centerplan's Jason Rudnick, the manager of the project, said he sent a letter back to the HSA today detailing progress on the project and what has led to cost overruns.
"At the end of the day we always thought we would have some sort of control over design to bring this back on budget and it never turned out to be that way," said Robert Landino with Centerplan.
Landino said the company was under the impression that the initial design build was the one to work off of but later received an entirely new design from the HSA that was more expensive.
In using the analogy of building a house, Landino said, "A lot was added to the home that wasn’t on the original plans and we simply had to estimate those and come up with a plan that reflected those changes."
Centerplan and DoNo hand delivered the letter to the HSA earlier today and later in the day, Mathews responded with a statement scolding the developer.
"DoNo Hartford LLC’s assertion that they did not have complete control over the design and construction of the ballpark is completely false. If there was a problem the time to share that important information was months ago," wrote Mathews.
The authority has held monthly meetings for most of the year and the topic of possible cost overruns was never brought up either in person or in documents.
The statement continued, "For nearly a year, DoNo Hartford LLC has been telling the stadium Authority and the public that the stadium is on schedule and on budget. To now tell us otherwise, at the eleventh hour, is completely unacceptable and we will take any and all necessary measures to protect the City’s interests.”
Mayor Pedro Segarra has described the spat as a "misunderstanding" but added that he's always felt the developer has been trustworthy partner for the city.
"That’s what they’ve been representing for the past year or so so I trust that will be the case," he said.
Landino said what the city wants and what was initially agreed to are different things and that has led to cost overrun. Landino said the company has attempted to make changes to the design and has even swapped out some subcontractors in order to control costs.
"Our original plan had two kitchens, the new plan has eight full service kitchens. That’s millions of dollars of cost and returning this to two or three or four kitchens was not an option, so having said that, that puts that on the table as a cost overrun which has to be made up in another way and then we went through an exercise to try to get the costs down and we just couldn’t get there."
Landino said the solution is for everyone with a stake in the project to sit down and discuss the future of the stadium and what the final product will look like.
"There’s ways to reduce it but the ways to reduce it require cooperation from both the team and the city and us and if everyone is willing to pitch in and do their share it’s a big exercise and it’s certainly going to require some funds in order to complete," Mayor Segarra agreed.
He said, "If something has come up that needs to be discussed I think the parties should sit down and work it out like good business people."
Photo Credit: NBCConnecticut.com